Overall Project Completion

Project Issued Date
Maunda lake beautification

Project Status: Completed
Last Updated: September 7, 2021

The Beautification plan envisions the creation of richly public amenities which will help to preserve the Masunda Talav rich cultural past through a comprehensive greening of Thane’s public realm. This new modernized look will provide an opportunity to unify the various neighbourhood and commercial corridors together into a new town vision.

Project Features:

  • Total Length of Project in Meters: 507.44
  • Stretch Name: Chintamani Chowk to Gadkari Rangayatan  
  • Components of the project
    • Seating areas for the general public
    • Walkway along lake periphery
    • Concrete cantilever viewing gallery
    • Khaugali Kiosk at 3 locations
    • Selfie point
Release of Tender : Tender Published
Issuance of Work Order : Work Order Issued
Date of Issue of Work order : 16/01/2020
Implementing Agency : M/s Shayona Construction
Cost of the Project : INR 5.22 Cr
Duration : 1 Year
Physical Progress : 100.00%
Financial Progress : 95.00%
Expenditure Till Date : INR 4.96 Cr