Pedestrian Improvement

Pedestrian Improvement – 8
Pedestrian Improvement – 7
Pedestrian Improvement – 6
Pedestrian Improvement – 5

Overall Project Completion

Project Issued Date
Pedestrian Improvement

Project Status: In-progress
Last Updated: July 23, 2020

Scope of Project

  • Footpath Renovation, Bollards fixing, New Kerb Stone Fixing, Traffic signages, street furniture, Landscaping, Street Art Painting, Sculpture etc.

  • Separation of Vehicular Traffic and Pedestrian Traffic in congested areas.

  • Wheelchair Accessibility and Tactile Paving for footpaths.

  • Estimated 12.km of roads in ABD area taken up for pedestrian improvement

Benefits to the citizen

  • Better footpath facilities for citizens

Project Status: Work is in progress.

Release of Tender : 17/02/2018
Issuance of Work Order : Work Order Issued
Date of Issue of Work order : 07/03/2019
Implementing Agency : M/s Pragati Enterprises
Cost of the Project : INR. 19.63 Cr
Duration : 9Months (Excluding Monsoon)
Physical Progress : 61.00%
Financial Progress : 60.00%
Expenditure Till Date :