Masunda lake Development Glass cantilever footpath
Please Login to View Projects
Overall Project Completion
1.Construction of cantilever glass viewing gallery of 1.5 m.
2.Increase in walkway up to 5 meters along Shivaji path road.
3.Increase in width of Shivaji path road
Benefits to the citizen:
- Preservation of Ecosystem.
-
Preservation of Open Spaces.
- Availability of more public space.
- Citizens will have the opportunity to closely observe the biodiversity of the lake.
| Release of Tender : | Tender Published |
| Issuance of Work Order : | Work Completed |
| Date of Issue of Work order : | 29/11/2018 |
| Implementing Agency : | M/s A E Infra Projects Pvt. Ltd. |
| Status : | Work Completed |
| Cost of the Project : | INR. 6 Cr |
| Duration : | 9 months |
| Physical Progress : | 100% |
| Financial Progress : | 100% |
| Expenditure Till Date: | INR. 6 Cr |