Fund Utilization

S.NoProject NameName Of The AgencyCost As per Work Order in Rs. CrWork Order DateBill Paid in Rs. Cr in June 2020 Bill Paid in Rs. Cr in July 2020Total Bills Paid in Rs. Cr For The Month of June and July 2020
1Multi-modal transit hub at the existing railway stationM/s NCC SMC SATIS JV Ltd260.8507/03/201912.2610.8023.06
2Construction of Underground parking at GaondeviM/s A E Infra Projects & NA Construction Pvt. Ltd Joint Venture23.5730/01/20191.681.68
3Pedestrian ImprovementsM/s Pragati Enterprises19.6307/03/20192.741.404.14
4Development of a Comprehensive sewerage systemM/s Atharva Construction22.8729/01/20191.041.04
5Remodelling of water supply networkM/s Atharva Construction-AE Infra (Joint Venture)47.2607/03/20192.912.91
6Construction of Strom water drainsM/s Bitcon India Infrastructure Developers Pvt. Ltd31.8514/06/20182.322.32
7Masunda lakefront development (Glass Cantilever Footpath Bridge)M/s A E Infra Projects Pvt. Ltd.6.0011/02/20191.951.95
8Development of Waterfront near Creek at Kavesar-Waghbil & Kolshet (Package 2) M/s BP Sangle Constructions Pvt. Ltd.50.5309/03/20181.651.65
9Development of Waterfront near Creek at Saket Balkum, Kalwa Shastrinagar, Kopri-Thane East (Package 3) M/S Dev Engineers 42.8409/03/20188.368.36
10Construction of Urban Restroom at Tembhi Naka/Court NakaM/s Kanchan Construction 0.3905/03/20190.290.29
11Construction of urban restroom at Police Sports Ground near Saket Biodiversity ParkM/s Soham Construction0.5005/03/20190.220.22
12Construction of urban restroom near Talavpali M/s Kanchan Construction 0.4103-09-20180.290.29
13Payment made to the Electrical contractor for Urban RestroomM/s Aahan Electronics0.100.10
14Smart Metering and Online Performance MonitoringM/s Jain Ceinsys JV121.0329/11/20185.595.59
Total15.0038.6053.60